Tennis Courts 5 - 8 Renovation Project
Anticipated Timeline: August 4 - September 12
(weather permitting...could be done earlier)

In an effort to complete the transformation of our tennis courts, we are scheduled to do significant renovations to courts 5 - 8 so they are comparable to our new courts. this project will be done in two phases and those phases will overlap timelines, weather permitting.

Phase 1: Installation of new MUSCO lights for courts 5 - 8.

Phase 2: Court resurfacing, net post replacement, install 2nd practice backboard on side of court 6, repair of perimeter fencing, and install new windscreen.

MUSCO lights: If you have seen our courts at night, you know that courts 1 - 4 have the new MUSCO lighting system and courts 5 - 8 have the old LED flood lights. We will be removing the current eight (8) light poles on 5 - 8 and they will be replaced with six (6) new 50' MUSCO lights. Our current light strength is an average of 12 and there are significantly higher and lower light levels throughout the courts. With new MUSCO lights, we will have an average 50 candle strength evenly spread along the courts with minimal spillage or wasted light.

The courts have not been resurfaced in nine years, so once the new poles are installed, Quality Courts and Outdoor will replace all court net posts (they are old and bending inward), repair the chain link fencing around the courts with new tension wires and repairing connector poles, and then cleaning and resurfacing all four courts. Once completed, Forest Oaks will install a new 2nd practice backboard on the side of court 6 and new windscreen similar to what is on courts 1 - 4.

Tennis Courts 5 - 8 Project Updates

Project Timeline

  • COURT 1 - 4 WILL NOT BE IMPACTED BY THIS PROJECT AND WILL REMAIN OPEN AND AVAILABLE FOR USE.

  • Wednesday, August 6

    • Temporary fencing starts to go up. Parking spots along courts 5 and 6 will be unavailable and fenced off.

    • WCID110 staff starts removal of light poles on Courts 5 - 8.​

    • Courts are available for use through the weekend during daylight hours only.

  • Friday, August 8 

    • MUSCO started deliveries of light poles and fixtures.

    • The lower tennis gate will be available for entering the facility.

  • Friday, August 9 - September 12 
    • Friday, August 9 - August 22:

      • Courts 5 - 8 offline until completion of project.

        • Forest Oaks staff starts removal of light poles

        • MUSCO installs new light poles

      • August 20 - September 12​​

        • Depending on weather, this part may be completed as early at September 5

        • Quality Courts and Outdoor replaced net posts, repairs fencing, resurfaces courts.​

        • Forest Oaks staff installs nets, court amenities, and new windscreen.

  • September 13 - Courts reopen for usage.​

    • This is our tentative reopening date. Inclement weather may delay project.​

In Existence Since May 9th 1968 Harris County WCID #110 All Rights Reserved.

The content in this website is provided by Harris County Water Control and Improvement District No. 110 ("HCWCID110 or District") for informational purposes only. This website and the information contained herein should not be relied upon or used as current information for the purposes of securities disclosure about the District, its financial condition, the bonds of the District, or property in the District. Persons should not rely upon information in this website when considering whether to buy, sell, or hold property within the District. The District files official continuing disclosure information at least annually in accordance with the rules and regulations of the securities and exchange commission. The District assumes no duty to update any information on this website at any time.