Forest Oaks Swim and Racquet Club
Master Plan Phase 1

Forest Oaks Pool and Recreation Building

The Forest Oaks Pool and pool house were two of the original facilities constructed in 1988 to create the Forest Oaks Swim and Racquet Club. Along with four tennis courts and original parts of Forest Oaks Park, these facilities were built to serve the residents of WCID110. Our District is a trailblazer in terms of dedicating space and funding for recreational facilities to meet a need for its residents. WCID110 was the first water district in the State of Texas to build these types of facilities and many district followed along the path we created. 

In January, 2026 the WCID110 Board of Directors has approved a master plan for the renovation and new construction of all buildings for Forest Oaks Swim and Racquet Club. This includes the pool, pool house, fitness center, and clubhouse. The master plan is three phases and will will take multiple years to complete. Phase 1 of the master plan will be the new Forest Oaks Pool and Recreation Building to be designed by GPD Group, an architecture firm based in Houston, TX. Landmark Aquatics is serving as the consultant firm for the pool. Langford Engineering (District Engineers) will oversee the project for the District and consult on storm water drainage. Phase 1 of the master plan has already begun and GPD Group is currently in the design phase of both the new recreation building and pool, working closely with Landmark Aquatics and Langford Engineering.

Phase 1 - Pool and Recreation Building

What will the new pool include?

  • The new pool will be oriented in a way to maximize the space available.

  • New pool entry and guard office for patron check in.

  • 8 lap lanes with 4' depth on one side and 7 1/2' deep on the other. Dive blocks will only be allowed on the deeper side of pool during swim meets (USA Swim safety guidelines).

  • Zero-depth entry with separation wall from deeper water of lap lanes.

  • Deep well with ~8-9' double-flume water slides.

  • Splash pad with safety surface and water features for small children.

  • Separate pump and filter building.

  • New aeration and heater systems for pool water temperature management.

    • We anticipate the pool will be open longer for adult swim and all-member access before/after summer.

  • New dive blocks.​

  • New lane lines.

What will the new Recreation Building include?

  • New guard office.

  • New swim team storage space.

  • New tennis pro office space and separate storage space.

  • Dedicated aquatics equipment storage room.

  • New bathrooms that will include two private spaces that include shower/toilet/sink/changing area in both men's and women's bathrooms.

  • New event space with kitchenette, storage, audio/visual, and access from tennis courts and pool deck.

    • This would be available for rentals and used during swim meets and tennis events.​

  • 2nd floor viewing deck that allows you watch both tennis and pool areas (elevator will be available).​

  • Built in shade structures on pool side.

  • Two outdoor showers.

  • Covered vestibule at pool entrance.

  • Covered breezeway space. 

Phase 1 Initial Timeline - Updated May 2026
Construction Phase November 2026 - April 2028

March - June 2026

  • Initial design of pool and recreation building.

  • Material, texture, and color pallet selection.

  • Stormwater planning and mitigation strategy.

July - October 2026

  • Construction plans finalized.

  • Project bid process.

  • Selection of general contractor for project.

  • Relocate entrance to fitness center for duration of construction project.

November - December 2026

  • Demo of current pool and pool house.

December 2026 - March 2028

  • Construction of pool and recreation building.

  • We will create online video access so residents can check in on construction during this project.

  • The pool will not be available for the 2027 summer. We are discussing plans for membership rate reduction or extension of active memberships to make up for the loss of an entire summer of pool access.

  • Forest Oaks Swim Team is working to find alternative locations for practices for the 2027 season and will have all away meets for the 2027 season.

April 2028

  • Construction completed!!!

  • Pool open for Forest Oaks Swim Team practices

In Existence Since May 9th 1968 Harris County WCID #110 All Rights Reserved.

The content in this website is provided by Harris County Water Control and Improvement District No. 110 ("HCWCID110 or District") for informational purposes only. This website and the information contained herein should not be relied upon or used as current information for the purposes of securities disclosure about the District, its financial condition, the bonds of the District, or property in the District. Persons should not rely upon information in this website when considering whether to buy, sell, or hold property within the District. The District files official continuing disclosure information at least annually in accordance with the rules and regulations of the securities and exchange commission. The District assumes no duty to update any information on this website at any time.