top of page

Forest Oaks Tennis Court
Construction Project

Forest Oaks Tennis Courts 1-4 are scheduled to be under construction from mid-March through end of May/beginning of June 2024. The anticipated construction timeline will take around three (3) months to complete once it has started. An exact timeline has not been set by the construction firm performing the work. Once a schedule has been created, updates will be provided on this page throughout the project.

Scope of the Project

The project will include the following:

  • Demo and removal of all current asphalt and substructure foundation. All new foundation and leveling will create a stronger base for the new court surfaces and minimize any potential cracking. New concrete courts will be use a post-tension system underlay which will also keep the courts from cracking and creating gaps on the surface.

  • Replacement of six current 30' tennis court light poles with four 60' state of the art MUSCO light systems. This will increase the light quality on courts 1-4 from the current average light level of 12 to an average light level of 50 with minimal spillage of light to the surrounding residential homes.

  • Replacement of all tennis net systems.

  • Replacement of all current fencing and windscreen with new fencing and new windscreen. 

  • Four pickleball courts will be lined on either side of the net on courts 7 and 8. New portable pickleball systems will be purchased by Forest Oaks for use. This would be a total of four pickleball courts.

    • We have asked the contractor for this change of the project and have not received confirmation as of 3/4/24.

  • Additional practice walls will be installed once the project is completed on Courts 1 and 4. This may be done during summer 2024 or later depending on the length of the project.

Tentative Schedule for Tennis Construction

ALL DATES ARE TENTATIVE AND WEATHER DEPENDENT!!!

  • March 18: Install construction fence, erosion control and relocate gate for courts 5-8

  • March 20: Start demo of the existing four tennis courts and sidewalks

  • March 27: Excavation

  • April 1: Installing base materials

  • April 4: Installing post tension cables and sleeves

  • April 11: Concrete pour

  • April 22: Stressing cables

  • April 23: Install the lighting

  • April 25: Install chain link fence

  • May 6: Installing sidewalks

  • May 10: Removal of construction fence and relocate the gate for courts 5-8

  • May 15: Court pavement coating

  • May 29: Install net posts and nets, windscreens

  • May 31: Jobsite clean up, sod as needed, final clean, construction fence remove

Forest Oaks Facility Entrance and Safety Fencing Restricted Areas

Facility Entrance and Safety Fencing Map

PROJECT UPDATES

  • 4/17/24: Classic Sports is putting in the first level of subgrade this week after finally getting the old stuff out. We ended up having to go deeper than we thought because the subgrades were in such bad condition. We are behind schedule but they hope to make up some of that time in the coming weeks.

  • 4/2/24: Classic Sports continues to demo the courts and prepare for the new subgrade of the new courts.

  • ​3/19/24: Lights and nets have been removed on Courts 1-4. Construction company will be onsite starting Wednesday, March 20 and safety fencing and laydown location will go up. Please see the parking map above for parking lot closures and traffic flow for March 20 - April 1. We will have signage up to help direct everyone to the only facility entrance that will be available next to the Fitness Center.

  • 3/12/24: The tentative court construction schedule has been added to the website. Courts 1-4 will go offline starting Monday, March 18. WCID110 staff will remove light poles on Monday, March 18.

  • 3/4: WCID110 staff will begin removal of the light poles on courts 1-4 starting at 8 a.m. on Friday, March 8. We anticipate contractor being onsite starting the week of March 11.

  • 2/24: we have asked the contractor to change our initial plan of having four pickleball courts lined on courts 1 and 2 and instead lining courts 7 and 8 as they are fenced and separated from all other courts. We have not received confirmation of this change in scope yet.

  • 2/23: First meeting is scheduled with construction team for Tuesday, 2/27 to go over project, timeline, and other information. 

  • 1/31/24: We have received the final contract for execution and that will be reviewed by our engineers and lawyers before going to the board for final approval during the 2/14 board meeting. We should see significant movement once the final approval is authorized and the construction company can provide us with the project schedule. As a reminder, based on their schedule, we will remove lights for courts 1-4 for the week before they start and then remove nets/poles/benches/windscreen/etc. on the courts for the day prior to them starting.

  • 1/19/24: The WCID110 District Manager and Office Manager met with the Tennis Committee, Rivera Tennis, and several of the recognized Forest Oaks tennis team captains to discuss court usage and scheduling during the construction project. It was a productive meeting and we are currently working on creating a court usage schedule which will be made available on the Tennis Courts page under Parks and Recreation tab.

  • 1/10/24: The Board approved the bid for the project and Langford Engineering will prepare the bid documents needed for the construction company. This takes 10-14 days as the construction company completes paperwork, provides additional required information, and starts to order equipment and supplies.

  • 12/13/23: The project was placed out for bid in December 2023 and one construction company submitted a bid for the project. That bid is under review by Langford Engineering, Inc. and the board will review the recommendation at the January 10, 2024 board meeting.

Forest Oaks Tennis Courts

​​Impact of Tennis Court Construction on Forest Oaks Members

  • To see temporary policies regarding tennis court usage during

       the construction project, click on the button below or go to the

       Parks and Recreation tab and scroll down to Tennis Courts and

       click on the image.

  • Court Access

    • Courts 5 - 8 will remain open and available for tennis players, Rivera Tennis, and league play but access to courts will be significantly impacted throughout this construction project.

    • All tennis court scheduling will be handled by Forest Oaks Office Manager.

    • Open rec users will NOT be guaranteed any specific days and times for access during peak hours of operation (Mondays through Fridays from 5 - 9 p.m.) due to Rivera Tennis programming and trainings as well as Forest Oaks approved league play. Courts 5-8 will be scheduled on an hourly basis to ensure we are using the courts efficiently for the differing needs of our stakeholders.

    • All Forest Oaks approved leagues will be approved as best as possible BUT court access and number of courts available will be reduced for any requests. This will lead to fewer games being played at any given time. It is encouraged that Forest Oaks teams request away games during this project if they want to have shorter competition times. Multiple leagues being played at the same time will be discussed with team captains and handled on a case by case basis.

    • All leagues that are not Forest Oaks will be denied reservation requests during the construction project.

  • Parking

    • Parking will be reduced in the lower tennis court lot once the construction team installs temporary fencing and security fencing for equipment and supplies. The parking spots nearest courts 5 and 6 will remain available and all individuals parking in those spots will have to walk to the main facility entrance to enter.

    • Parking will be allowed in the upper parking lots nearest the clubhouse during the construction project without penalty as long as valid parking pass is displayed.

    • Those without parking tags can use Forest Oaks Park parking lot.

  • Court Gate Entrances

    • The two tennis court access gates will be unavailable for use once the construction team installs temporary fencing. All tennis players will have to enter the facility through the main facility gate nearest the fitness center.

  • Lighting and Court Nets

    • Prior to the start of construction, the current light poles on courts 1-4 will be removed. We anticipate removing them one week prior to the start of the demo.

    • One day prior to start we will remove:

      • All nets and posts

      • All fence shades and court bench/shades

      • All windscreen

      • All signage and displays along fence.

  • General Impact

    • Once demo begins, there will be considerable noise, dust, debris, and workers present.

    • Forest Oaks staff will continue to blow off courts 5-8 in the mornings around 7:30 a.m. and, when possible, in the afternoon around 2 p.m. Additional court cleanings will not be performed after 3 p.m. by WCID110 staff. Rivera Tennis or team captains can blow off courts as needed.

bottom of page